A leaking shower is one of the most expensive call-backs in the trades. The water usually goes unnoticed for months, the damage spreads into framing and floors, and the fix means ripping out finished tiles. The good news is that most leaks come from the same handful of weak spots. Get those right and the membrane does its job for decades.
This guide covers the general order of work and the details that matter. It is not a replacement for your local building rules or the manufacturer’s instructions for the system you’re using. Always follow both. In New Zealand that means the Building Code (clause E3 and its acceptable solutions). In Australia, wet-area waterproofing is covered by AS 3740, and some states require a licence to do it.
Before you start: use one complete system
A membrane, its primer, its reinforcing tape and its sealants are designed and tested to work together. Mixing products from different brands can cause poor adhesion and void the manufacturer’s warranty. Pick one system and use every part of it as the data sheet says.
Step 1: Get the substrate right
The membrane is only as good as what it’s stuck to.
- Use substrate materials made for wet areas, fixed to the manufacturer’s spacing
- Make sure it’s sound, flat, clean, dry and free of dust, oil and old adhesive
- Fill gaps and fix any movement. A membrane can’t bridge a floor that flexes.
- Check moisture levels on concrete, especially new screeds
Step 2: Make sure the floor falls to the waste
Water should run to the waste without ponding anywhere. Form the fall in the substrate or screed before waterproofing, to the gradient your local standard and the tile manufacturer require. Don’t rely on building up tile adhesive to create the fall. A simple check: pour a bucket of water on the formed floor and watch where it goes.
Step 3: Prime
Apply the system’s primer to every surface the membrane will cover, and let it dry for the time stated. Primer improves adhesion and seals dusty or porous surfaces. Skipping it is a common cause of a membrane peeling away.
Step 4: Treat the junctions before the main coats
Most leaks start at the junctions. Do these first, with the system’s reinforcing tape, bandage or bond-breaker:
- Wall-to-floor junctions: buildings move, and this joint moves the most
- Internal corners, wall to wall
- Sheet joints in the wall linings
- Hob, step-down and screen-channel details
The point of a bond-breaker or flexible bandage at a junction is to let the membrane stretch over a small movement instead of cracking.
Step 5: Seal the waste and every penetration
- Floor waste: use a puddle flange (or the waste detail your system specifies) so the membrane laps into it, and any water that gets under the tiles can still drain away
- Taps, mixers and shower roses: seal every pipe penetration with the collars or sealant the system calls for. Penetrations at the back of a shower are the most common leak point after the floor waste.
- Niches and shelves: treat every edge and corner of a niche like an internal corner
Step 6: Apply the membrane to the right thickness
- Apply the number of coats the manufacturer specifies, usually at least two, letting each dry between coats
- Lay coats in different directions, and use a contrasting colour for the second coat where available, so you can see you haven’t missed a patch
- Build up the minimum dry film thickness on the data sheet. A wet film gauge is cheap and takes the guesswork out.
- Take the membrane up the walls to at least the height your standard requires, and past the shower area onto the floor as required
Step 7: Let it cure, then flood test
Don’t tile until the membrane has fully cured for the time the manufacturer states. Cool or damp weather can slow curing a lot.
Many installers then flood test the shower floor: block the waste, fill to just below the top of the hob or screen line, mark the level and leave it, commonly for 24 hours. If the level drops or water shows up anywhere it shouldn’t, find and fix the leak now, when it’s cheap.
Step 8: Tile without damaging the membrane
- Use an adhesive compatible with the membrane, and get full coverage under floor tiles so there are no hollows for water to sit in
- Don’t fix anything through the membrane after it’s done unless the system shows how to seal it
- Use flexible sealant, not grout, at changes of plane (wall to floor, internal corners) and around fixtures. Grout cracks there because those joints move.
The leak hotspots to double-check
- Puddle flange or waste not properly lapped into the membrane
- Tap and mixer penetrations not sealed
- Wall-to-floor junction with no bandage or bond-breaker
- Membrane too thin, or patches missed
- Tiling before the membrane had cured
- Grout instead of flexible sealant at corners and junctions
- Not enough fall, so water ponds against the walls
Keep a record
Take photos at each stage: substrate, primer, junction treatment, each membrane coat, and the flood test with the level marked. Note the product names and batch numbers. If there’s ever a question later, a photo record of a correctly installed membrane is the best evidence you can have, and many manufacturers’ warranties depend on it.
For a deeper reference on membranes, falls and detailing you can keep on your phone, see WaterProof Pro.
Common questions
Why do most showers leak?
Most leaks come from the same few weak spots: a waste not properly lapped into the membrane, unsealed tap and mixer penetrations, untreated wall-to-floor junctions, a membrane that is too thin, tiling before it cured, grout instead of flexible sealant at corners, and not enough fall.
How do you flood test a shower?
Once the membrane has fully cured, block the waste, fill to just below the top of the hob or screen line, mark the level and leave it, commonly for 24 hours. If the level drops or water shows up anywhere it shouldn’t, find and fix the leak before tiling.
How many coats of waterproofing membrane does a shower need?
Apply the number of coats the manufacturer specifies, usually at least two, letting each dry in between. Lay coats in different directions and build up the minimum dry film thickness on the data sheet. A wet film gauge takes the guesswork out.